« Back to news story list

New Housing Association—Crieff High Street

Tuesday, April 28th, 2015

IMG_0931

Skene Group Ltd were appointed as groundwork’s contractor on a development in Crieff. The demolition of the existing public house was undertaken ny others prior to Skene Group Ltd being appointed. The works package involcved working in around temporary support system where existing buildings were being retained. The concrete foundations for the new development were designed as such that the existing buildings were supported during the operation. Skene Group Ltd successfully installed the foundations, tanking membrane, drainage and poured floor slabs for the new development under very onerous conditions and limited working room. The implementation of small plant and clever shuttering by the Skene Group Ltd shuttering joiners resulted in what was a very difficult job coming together, allowing the steel frame to be erected.

« Back to news story list