Aberdeen—Student Accommodation

Monday, September 15th, 2014

024

New Student Accommodation—Aberdeen.  All the sub structure work is now completed and SKENE GROUP LTD are off site awaiting on the external works package being made available to them for concluding the project.  The sub structure works involved cutting down steel tube driven casings, filling with concrete, installing reinforcing bars, tying in the ring beam foundations, installing sacrificial shuttering and pouring the concrete.  The floor slabs were cast and polished finished prior to protecting during the build process.