Minto Business Park—Aberdeen

Thursday, January 23rd, 2014

The initial concrete pour has been undertaken at the site this week 16/01/14. The current sie pro-gress has been good with the steel structure erected on the back of Skene Group Ltd pouring the
foundation. The car parking areas have been formed and blocked prior to the Principle Contractor
landing their temporary welfare facilities. Skene Group ltd have concluded drainage works to the
building and car parking along with applying base tar to the access road. The conclusion of the in-ternal floors shall result in Skene Group then preparing the external yard for concrete works.

 